Construction Change Orders: How Subcontractors Protect Scope and Get Paid

How subcontractors handle construction change orders: written approvals, pricing extra work, time-and-material tickets and schedule impacts.

Get it in writing before you build it

A verbal request on site is easy to forget and hard to bill. Most subcontract agreements require written authorization before extra work starts. If the work is urgent, send a short email or text the same day confirming what was asked and who asked.

What a clear change order includes

Make each change order easy to approve:

  • A description of the added, removed or changed work
  • The drawing, RFI or field direction that caused it
  • Labor, material and equipment cost, with your markup
  • Any added working days
  • Signature lines for the person authorized to approve it

Time-and-material tickets

When the scope cannot be priced up front, track time and material daily. Have the superintendent sign each ticket while the work is fresh, and attach material receipts.

Schedule impacts

Changes often move other work. Say in the change order if it affects your start or finish date so the time is approved with the price.